Daily Field Report

Date :12/31/2024
Project No :2021C060
Client Company :Pulte Group
Arrival Time :12/31/2024 11:00
Onsite Hours :03:30
Name of the Project :Suncity - Peachtree
Project Location :Griffin, GA
Weather :Sunny
Departure Time :12/31/2024 14:30
ASEC Technician Name :Micah Aycock

Observations/Finding

Our representative was on site to perform a foundation inspection for Lot 56 Pod 21.  Dynamic Cone Penetrometer (DCP) testing indicated that the foundations were suitable for a soil bearing pressure of 2,000 psf and concrete placement. In-place rebar was found to meet job specifications for size, spacing and quantity.

Please notify us if you have any questions regarding this report.

 

 

 

Technician Signature / DateMicah Aycock, December 31, 2024
Reviewer Name / DateKenneth Mosman, January 12, 2025