Daily Field Report
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
Seven Hills: Amenities
Due to the Excessive rainfall from the previous days, the job site remained saturated with excessive moisture. To address this, the contractor began clearing the slopes and facilitating the drying process using a Komatsu PC360LC excavator and a Komatsu 39PX dozer. These machines were utilized to effectively remove excess moisture, level the surface, and prepare the site for the next phase of construction. The combination of equipment helped improve site conditions by enhancing drainage and accelerating the drying of the wet soil. No backfilling was performed during this process.
Nature Walk: Lot 995
Lot 995 was dozed and cleaned using a Komatsu 39PXI dozer and a Komatsu PC240LC excavator. The slopes at the rear of the lot were corrected by adding dirt with dump trucks, while the shaping and management of the slopes were handled by the Komatsu machinery. No backfilling was done except for the slopes. Stone was encountered during the slope backfilling, and the necessary backfill instructions were provided to the superintendent for proper handling. Additionally, the probe was checked to ensure all conditions were met.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.