- Home
- Daily Field Report Report ID: 73272
- Edit Download Report
Daily Field Report
Date :11/16/2024
Project No :2024C168
Client Company :CCG
Arrival Time :11/16/2024 8:30
Onsite Hours :03:00
Name of the Project :Reserve @ Gum Springs
Project Location :Jefferson
Weather :sunny
Departure Time :11/16/2024 11:30
ASEC Technician Name :Aminullah Azimi
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
- The placement and compaction of backfill soils for water line in the form Lots# 234 to lot#235 and lot#236 to lot#181, lot#182, lot#183. continued this day.
- Since there was rain the day before, the contractor did not backfill due to the wet material.
- Note: there were a few test failures in the sewer trench between MHSA8, MHSB1 and MHSB2 the material was not good it was recommended to undercut about 1.5 feet and replace it with red soils and recompact it.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.
Technician Signature / DateAminullah Azimi, November 16, 2024