Daily Field Report

Date :11/01/2024
Project No :2024C217
Client Company :Artisan
Arrival Time :11/01/2024 08:10
Onsite Hours :08:45
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :cloudy
Departure Time :11/01/2024 16:50
ASEC Technician Name :Vamsi Polisetty

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Nature walk: lot 1055 & 1056

  • Next layer of fill is started in lot 1056, dozing and levelling is done with CAT953K
  • compaction is done with Hyundai HR70C, as it is cloudy and rainy, the next fill is approved using the probe and proof rolling technique

Seven Hills: Amenities

  • Upon arrival, the contractor was engaged in adding fill near the Pickle ball court parking using a Komatsu PC 360LC and cut from the west of the job site. Dirt was being transported with two tandem dumps, while dozing and leveling were performed with a Komatsu D85EX for the next layer.
  • rocks and Boulders are found in the back fill, necessary instructions are made for the proper compaction using the proof roll method and also using D85EX.
  • all the slopes are dozed and levelled with Komatsu 39PX.
  • cloudy and rainy, so the next fill is approved using the probe and proof rolling technique

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateVamsi Polisetty, November 1, 2024