Daily Field Report

Date :10/28/2024
Project No :2024C202
Client Company :CCG
Arrival Time :10/28/2024 07:30
Onsite Hours :9:15
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :
Departure Time :10/28/2024 16:45
ASEC Technician Name :Solomon Cherie

Observations/Finding

In this day, extensive fill and packing activities were carried out. And consecutive nuclear and probing compaction tests were also done. Though the giage read 95-98%, proof rolling shows no pumping suggesting very high compaction, a minimum of 98. As the moisture is also within the proctor limit and rollling is also repeatedly done, the compaction is pretty good.

The building pads 99-101 and the road close to subgrade.

Technician Signature / DateSolomon Cherie, October 28, 2024