Daily Field Report

Date :09/23/2024
Project No :2024C202
Client Company :CCG
Arrival Time :09/23/2024 15:00
Onsite Hours :02:00
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :sunny
Departure Time :09/23/2024 17:00
ASEC Technician Name :

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

  • Upon arrival, the contractor was engaged in excavating a CAT 349E on the south of the project site for a detention pond. Suitable soils were being transported with tandem dump trucks CAT 745, while dozing and leveling were performed with a Komatsu 512PXi.  Compaction work was carried out using a CAT 815F2
  • Various size boulders were used in backfilling under the pond area as per instructions.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you

 

Technician Signature / DateVamsi Polisetty, September 23, 2024
Reviewer Name / DateKenneth Mosman, October 23, 2024