Daily Field Report

Date :09/30/2024
Project No :2024C116
Client Company :Peeples Owner, LLC
Arrival Time :09/30/2024 09:00
Onsite Hours :08:00
Name of the Project :Peeples Valley Rd, Overlook at Pettit
Project Location :Cartersville
Weather :Cloudy
Departure Time :09/30/2024 17:00
ASEC Technician Name :Fawad Shagiwal

Observations/Finding

As requested the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawings/specifications, applicable codes and material submittals.
The following observations were observed on the site this day.

  • The placement and compaction of backfill soil of lots#89 to 97 was completed and 01 foot lift being placed and compacted using sheep food (CP54B), (RA30), (D61PX) and (CAT330) equipments.
  • Construction and placement of concrete road curbs for lots #62 to 97 was completed.
  • Excavation and preparation of trenches for placement and installation of sewer lines pipes and manholes was in progressed.
  • Installation and placement of sewer lines pipes and manhole SSA5 , SS-P-B1 and SS-P-B2 were in progressed.

Technician Signature / DateFawad Shagiwal, September 30, 2024