Daily Field Report

Date :09/20/2024
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :09/20/2024 07:45
Onsite Hours :07:45
Name of the Project :Lakeside Sub. - Lovers Lane, Calhoun
Project Location :Calhoun
Weather :Sunny
Departure Time :09/20/2024 15:30
ASEC Technician Name :Solomon Cherie

Observations/Finding

Sewer line b/manhole B1.8 and B3.0 was backfilled and one more lift will be done next day.

Whereas storm line through BB9, BH2 and BH3 is also backfilled but the last lift is not rolled yet.

Storm lineBB9, BH2, BH3, with the final lift not packed

Sewer line B1.8-B3.0 while backfilling and rolling.

Technician Signature / DateSolomon Cherie, September 20, 2024