- Daily Field Report Report ID: 70323
- Edit Download Report
Daily Field Report
Date :09/16/2024
Project No :2024C168
Client Company :CCG
Arrival Time :09/16/2024 8:45
Onsite Hours :9:45
Name of the Project :Reserve @ Gum Springs
Project Location :Jefferson
Weather :cloudy
Departure Time :09/16/2024 18:30
ASEC Technician Name :Aminullah Azimi
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
- The placement and compaction of fill soils for the sewer line trench between MHSA18 to MHSL1 and storm water trench between MHMHA12.1, MHA12.2, MHB9, MHB9.MHB10 and fill for Lots #11, 12, 13, 14, 15, 16, 17, 18 and 19, continued this day.
- At the time of arrival, our representative observed that work was in progress with1-foot lifts being placed and compacted using CP56B and trench compaction equipment. Compaction testing was performed using a Troxler nuclear density gauge, along with general probing using a 3/8″ diameter probe rod.
- Density test results indicate that most of the compacted materials met the project requirement of 95% of the maximum dry density obtained by a Standard Proctor ASTM 698.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.
Technician Signature / DateAminullah Azimi, September 16, 2024
Reviewer Name / DateKenneth Mosman, October 20, 2024