- Daily Field Report Report ID: 69823
- Edit Download Report
Daily Field Report
Date :09/10/2024
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :09/10/2024 08:00
Onsite Hours :08:30
Name of the Project :Lakeside Sub. - Lovers Lane, Calhoun
Project Location :Calhoun
Weather :Sunny
Departure Time :09/10/2024 16:30
ASEC Technician Name :Solomon Cherie
Observations/Finding
- The total area of down cut at lots 125-131 was 9105 sq.ft whereas the volume of soil down cut was 27315 cubic ft.
- Before starting backfill the cut area was proff rolled (see attachment) and bumping areas were identified and cut.
- The grading company was trying to do backfill using rocky dirt but I strongly advise not to do because it will not be compacted. The contractor is informed and accepted.
- Right now they are using wet dirt and I suggested to do one lift and plough it to get dry for tomorrow. And the contractor is doing that (see the attachment)
Back filled and ploughed to get dry
Proff rolling before back fill
Technician Signature / DateSolomon Cherie, September 10, 2024