Daily Field Report

Date :09/09/2024
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :09/09/2024 08:00
Onsite Hours :08:00
Name of the Project :Lakeside Sub. - Lovers Lane, Calhoun
Project Location :Calhoun
Weather :Partly cloudy
Departure Time :09/09/2024 16:00
ASEC Technician Name :Solomon Cherie

Observations/Finding

The grading companies are working on sewer and storm line, though it is time taking.

The sewer line 10.2-10.3 pipe line is done. They put proper gravel beneath before soil back fill (see the attachment).

The storm line pipe burying is not also done yet, but they did backfill b/n BB8 & BB9 (see attachment) and compaction tests is done.

Sewer line 10.2-10.3

Storm line b/n BB8 and BB9

Technician Signature / DateSolomon Cherie, September 9, 2024