Daily Field Report

Date :09/04/2024
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :09/04/2024 08:00
Onsite Hours :9:00
Name of the Project :Lakeside Sub. - Lovers Lane, Calhoun
Project Location :Calhoun
Weather :
Departure Time :09/04/2024 17:00
ASEC Technician Name :Solomon Cherie

Observations/Finding

During the day I was supervising the gav and soil backfill at the sewer site. In addition, I did nuclear tests and exercise at different locations and familiarize my self with the machine together with Russ.

The machine and the model doing soil.compaction

The nuclear gauge at various tests

Sewer line filled with gav (rock).

Addingbwater on gav before compaction

Sewer line backfilled with soil and cmpacted

Technician Signature / DateSolomon Cherie, September 4, 2024