Daily Field Report

Date :08/30/2024
Project No :2024C195
Client Company :CWM
Arrival Time :08/30/2024 18:00
Onsite Hours :04:15
Name of the Project :Ramp 21 Replacement
Project Location :HJAIA
Weather :Clear sky
Departure Time :08/30/2024 22:15
ASEC Technician Name :Solomon Cherie

Observations/Finding

Upon arrival, we did:

1) Moisture tests

2) Stripped two sets of seven beams each,

3) Done air slump temperature and unit weight of truck number one

4) Conducted same test in item number three and casted one set of seven beams,

5) Done LS and LS tests and casted four cylinders of 6×12,

6) Clean all equipment and working area and put all equipment in order of their location.

Technician Signature / DateSolomon Cherie, August 30, 2024