Daily Field Report

Date :08/29/2024
Project No :2024C116
Client Company :Peeples Owner, LLC
Arrival Time :08/29/2024 08:45
Onsite Hours :08:15
Name of the Project :Peeples Valley Rd, Overlook at Pettit
Project Location :Cartersville
Weather :Sunny
Departure Time :08/29/2024 17:00
ASEC Technician Name :Fawad Shagiwal

Observations/Finding

As requested the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawings/specifications, applicable codes and material submittals.
The following observations were observed on the site this day.

  • The placement and compaction of backfill soil of lots#46 to 61 was in progressed using sheep food (CP54B), (RA30), (D51PX) and (CAT330) equipments.
  • Excavation and preparation of trenches for placement and installation of storm water lines pipes, manholes and sewer lines pipes, manholes were in progressed.
  • Installation and placement of sewer lines pipes and manhole SSA2 were in progress.
  • Installation and placement of storm water line pipes from manhole CIA7 to CIA8 was in progressed.
  • Installation and placement of storm water pipes and manholes # CIA6 and CIA7 were completed.
  • 01 foot lift being placed and compacted at the trench between storm water manholes CIA7 and CIA8 using trench packer (BMP8500) and sheep food (CP54B)equipments.
  •  At the construction entrance down hill road side 15CR Graded AGGR Base material was placed and was leveled, eventually preparation of base course for asphalt paving was in progressed.

Technician Signature / DateFawad Shagiwal, August 29, 2024