Skip to content

Daily Field Report

Date :08/20/2024
Project No :2024C116
Client Company :Peeples Owner, LLC
Arrival Time :08/20/2024 08:45
Onsite Hours :08:15
Name of the Project :Peeples Valley Rd, Overlook at Pettit
Project Location :Cartersville
Weather :Sunny
Departure Time :08/20/2024 17:00
ASEC Technician Name :Fawad Shagiwal

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawings/specifications, applicable codes and material submittals.
The following observations were observed on the site this day.

  • The roadway along the north side of the permanent storm water pond (dimensions of L=200 feet, Width=35 feet, Depth=4 feet), were found to be soft and wet and unstable.  Continued removal of these wet soils and replacement/compaction of drier materials continued.
  • Excavation and preparation of trenches for placement and installation of storm water lines and manholes and sewer lines and manholes progressed.
  • Installation and placement of sewer lines and manhole SSD4 continued.
  • Installation and placement of storm water lines and MH CIA4 progressed.
  • One (1) foot lifts were being placed and compacted between storm water manholes CIA3 and CIA4 using trench packer (BMP8500) equipment.
  • Work was in progress at the construction entrance road with one (1) foot lifts being placed and compacted using sheeps-foot (CP54B) and (D51PX) equipment.

Technician Signature / DateFawad Shagiwal, August 20, 2024
Reviewer Name / DateKenneth Mosman, October 21, 2024