Daily Field Report

Date :08/07/2024
Project No :2024C195
Client Company :CWM
Arrival Time :08/06/2024 17:00
Onsite Hours :11:15
Name of the Project :Ramp 21 Replacement
Project Location :HJAIA
Weather :
Departure Time :08/07/2024 04:15
ASEC Technician Name :Solomon Cherie

Observations/Finding

As requested, our AS Engineering & Consulting LLC representative was on site to perform the following:

1) Moisture tests were performed on sand materials placed.

2) Slump tests and one set of 5 cylinders were cast.

3) Air, slump, temperature and unit weight tests for the 1st truck of the normal batch were performed.

4) The above tests and two sets of seven beams were cast from trucks #23 & #56.

There was some delay in concrete placement throughout the pour due to equipment issues.

Technician Signature / DateSolomon Cherie, August 7, 2024
Reviewer Name / DateKenneth Mosman, August 11, 2024