Date :08/02/2024
Project No :2024C195
Client Company :CWM
Arrival Time :08/02/2024 19:00
Onsite Hours :01:15
Name of the Project :Ramp 21 Replacement
Project Location :HJAIA
Weather :Sunny
Departure Time :08/02/2024 20:15
ASEC Technician Name :Solomon Cherie

Observations/Finding

As requested, our AS Engineering & Consulting LLC representative arrived on site to observe the following:

Upon arrival our representative performed a moisture test.   Not long afterwards, ASEC was informed that activities were to be terminated for the day. Yesterday’s concrete test specimens we stripped and placed into curing.

Technician Signature / DateSolomon Cherie, August 2, 2024