- Concrete Test Report Report ID: 68343
- Edit Download Report
Concrete Test Report
Date :08/01/2024
Project No :2024C195
Client Company :CWM
Arrival Time :07/31/2024 18:00
Onsite Hours :08:00
Name of the Project :Ramp 21 Replacement
Project Location :HJAIA
Weather :Cludy
Departure Time :08/01/2024 02:00
ASEC Technician Name :Solomon Cherie
Concrete Placement Information
Location(S):
Testing:
2 Set of concrete specimens (7 Cylinders per set) were cast during the cast-in-place concrete pour at the above referenced location, in accordance with ASTM C31. The cylinders will remain on site for the initial 24-48 hrs curing.
Compliance:
Field placement of concrete appeared to be in accordance with the project specifications (i.e., slump, temperature, etc) (refer to remarks below)
Deviations and/or noncompliances were noted during the field placement (refer to remarks below)
Cylinders
Pick Up: 2 Sets of concrete cylinders/ 7 cylinders per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Pick Up: 2 Sets of concrete cylinders/ 7 cylinders per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Field Curing:
Cylinders were stored for the initial 24 hours
Near the poured structure
In an insulated curing box
Other
Remarks:
The following was completed:
1) Stripped one set of 7 beams.
2) Conducted air content, concrete temperature, slump, and unit weight testing for freshly placed concrete.
3) Four separate air content tests indicated an air content higher than specifications. The fifth test indicated air content within specifications.
4) Two (2) sets of beams were cast for 189 and 405 cubic yards placed.
Technician Signature / DateSolomon Cherie, August 1, 2024
Reviewer Name / DateKenneth Mosman, August 06, 2024