Daily Field Report

Date :07/31/2024
Project No :2024C195
Client Company :CWM
Arrival Time :07/29/2024 21:00
Onsite Hours :06:45
Name of the Project :Ramp 21 Replacement
Project Location :HJAIA
Weather :cloudy
Departure Time :07/30/2024 03:45
ASEC Technician Name :Solomon Cherie

Observations/Finding

As requested, our AS Engineering & Consulting LLC representative arrived on site to observe/perform the following activities:

  1. Stripped beams casted in previous concrete placement.
  2. Air, temperature, slump and unit weight tested for the first truck placement.
  3. Performed air content, temperature, slump and unit weight tests followed by the casting of seven test cylinders at the placement of 117 cubic yards.
Technician Signature / DateSolomon Cherie, July 31, 2024
Reviewer Name / DateKenneth Mosman, August 06, 2024