Daily Field Report

Date :06/13/2024
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :06/12/2024 08:00
Onsite Hours :33:30
Name of the Project :Lakeside Sub. - Lovers Lane, Calhoun
Project Location :Calhoun
Weather :sunny
Departure Time :06/13/2024 17:30
ASEC Technician Name :Marteze Jeter

Observations/Finding

At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications.  The following observations were made:

Our representative observed the contractor place backfill using CAT 336 and CAT 3151 equipment to excavate the main trench (and place pipe) near the entrance. Contractor used a Komatsu PC490 LC excavator to dig trench and place storm drain and MH 8.7,8.8, 8.9. Once storm drain was placed contractor then placed No. 57 stone to 6 inches above the storm drain. Contractor compacted using walk-behind and sheeps-foot roller.

Our representative observed contractor usinga  CAT 3364 excavator to dig sewer trench between MH 6.8-6.9. Once contractor excavated the trench, main sewer line was placed. Contractor used CAT 938K loader to bring in No. 57 stone. They placed the No. 57 stone to 6 inches above the drainpipe. Backfill was then placed and compacted with a walk-behind roller.

Contractors also used a Komatsu PC490 LC excavator to dig trench and lay storm drain between MH Ae.4-Ae.5. Once storm drain was placed, contractor placed No. 57 stone to 6 inches above pipe. Backfilling and compaction with a walk-behind roller then proceeded.

Observations:

  1. Backfilling Activities:
    • Backfilling was in progress for the sanitation sewer, and storm drain
  2. Sewer Installation:
    • Sewer main was placed between MH 8.7,8.8,8.9
    • Storm drain was placed between MH 6.8-6.9, Ae.4-Ae.5
  3. Compaction Status:
    • Compaction was carried out, using walk behind roller

Conclusion: The ongoing backfilling and storm drainpipe installation activities are progressing as planned, with considerations for lift sizes and temporary measures discussed with the foreman.

Technician Signature / DateMarteze Jeter, June 13, 2024
Reviewer Name / DateKenneth Mosman, July 19, 2024