- Daily Field Report Report ID: 67348
- Edit Download Report
Daily Field Report
Observations/Finding
At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to visually observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site this shift:
Incident Summary
A request was made to perform a proof-roll at 9:00 AM on the future deceleration lane. Upon arrival, it was observed that the future deceleration lane subgrade was not ready for proof-rolling, leading to the postponement of the scheduled activity. The foreman on-site decided to delay the proof-roll to the next day.
Sequence of Events
- Proof Roll Request
- Requested Time: 9:00 AM
- Arrival at Site
- Time of Arrival: 9:00 AM
- Upon arrival, it was observed that the deceleration lane was not in a condition to perform the proof roll. Necessary preparations and compactions were incomplete.
- Assessment of Deceleration Lane Condition
- Observed Condition:
- The surface was not adequately prepared.
- Required compaction levels were not achieved.
- Presence of loose material and unfinished grading.
- Observed Condition:
- Decision to Delay
- Decision By: On-Site Foreman
- The foreman decided to delay the proof-roll to allow for the completion of required preparations.
Analysis
- Preparation Issues
- Incomplete preparation of the deceleration lane hindered the scheduled proof-roll. This includes inadequate grading, compaction, and removal of loose materials.
Immediate Actions Taken
- Communication
- Confirmed the new scheduled time for the proof-roll.
- Preparation Plan
- Coordinated with the foreman to ensure all necessary preparations for the deceleration lane are completed before the rescheduled proof-roll.
Conclusion
The inability to perform the proof-roll as scheduled was due to the unprepared condition of the deceleration lane subgrade. Immediate actions have been taken to address the issue, and a new proof-roll has been scheduled for the next day.