Daily Field Report
Date :06/13/2024
Project No :2024C116
Client Company :Peeples Owner, LLC
Arrival Time :06/13/2024
Onsite Hours :
Name of the Project :Peeples Valley Rd, Overlook at Pettit
Project Location :Cartersville
Weather :Sunny
Departure Time :06/13/2024
ASEC Technician Name :Russell Hendrix
Observations/Finding
At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to visually observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site:
A meeting was convened to address issues affecting the detention pond area and to discuss potential solutions. This report details the key points discussed, the engineer’s recommendations, and the agreed-upon actions.
Key Points Discussed
- Current Condition of Detention Pond Adjacent Area
- Assessment of the affected area, including erosion, soil stability, and structural integrity.
- Review of previous inspections and reports by the soil technician.
- Impact on Project Timeline
- Discussion on how the current issues are impacting the project timeline and budget.
- Identification of immediate and long-term implications.
- Recommendations by ASEC Engineer
- 2-Foot Bridge Lift:
- The engineer recommended implementing a 2-foot bridge lift to stabilize the affected area.
- Possible Need for Soil Cement:
- The engineer suggested that soil cement might be needed at a later date to further reinforce the area if initial measures are insufficient.
- 2-Foot Bridge Lift:
Engineer’s Recommendations
- 2-Foot Bridge Lift
- Purpose: To stabilize and elevate the affected area, preventing further erosion and improving structural integrity.
- Materials and Methods: Detailed specifications for the materials and construction methods to be used.
- Soil Cement (Contingency Plan)
- Purpose: To provide additional stabilization if the 2-foot bridge lift does not suffice.
- Materials and Methods: Guidelines for the potential application of soil cement, including mix design and application techniques.
- Monitoring: Continuous monitoring of the area post-lift to determine the necessity of soil cement.
Agreed-Upon Actions
- Immediate Implementation of Bridge Lift
- Commence the construction of the 2-foot bridge lift as recommended by the engineer.
- Assign roles and responsibilities to the grading foreman, soil technician, and construction crew.
- Ensure procurement of necessary materials and equipment.
Affected area
Technician Signature / DateRussell Hendrix, June 13, 2024
Reviewer Name / DateKenneth Mosman, July 19, 2024