Daily Field Report
Observations/Finding
At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to observe the contractor’s work activities from a quality standpoint to assure compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site this shift:
A construction meeting was convened to discuss the specific requirements for the upcoming Gum Springs project, verifying that all parties are aligned and prepared for the project’s commencement. This report details the key points discussed, decisions made, and specific requirements set for the soil testing.
Key Points Discussed
- Project Scope and Timeline
- Overview of the Gum Springs project scope.
- Timeline of project milestones.
- County Requirements
- Specific requirements and standards set by the Jefferson County Water Department.
- Emphasis on compliance with local regulations and environmental guidelines.
- Soil Testing and Reporting
- Importance of accurate and timely soil testing.
- Specific requirements for soil testing procedures and documentation.
Specific Requirements for Soil Technicians
- Monthly Reports
- Soil technicians are required to submit detailed soil test reports by the 15th of each month.
- Reports must include data on soil composition, compaction, moisture content, and any other relevant parameters.
- Reports should also provide analysis and recommendations based on test results.
- Testing Standards
- All soil testing must adhere to ASTM standards and any additional county-specific guidelines.
- Soil technicians must ensure all equipment is calibrated and maintained according to industry standards.
- Documentation and Record-Keeping
- Maintain comprehensive records of all soil tests conducted, including dates, locations, and results.
- Ensure that all records are easily accessible for review by project managers and county officials.
Decisions Made
- Approval of Soil Testing Schedule:
- The proposed schedule for soil testing and reporting was approved by all parties.
- Compliance with Reporting Deadlines:
- A firm deadline of the 15th of each month was established for the submission of soil reports.
Action Items
- Soil Technicians:
- Begin preparations for soil testing in alignment with the project timeline.
- Ensure all reports are submitted by the 15th of each month without fail.
- Project Management:
- Monitor the progress of soil testing and reporting.
- Coordinate with soil technicians to address any issues promptly.
- County Officials:
- Review submitted soil reports for compliance with county requirements.
- Provide feedback or additional requirements as necessary.
Conclusion
The meeting at the Jefferson County Water Department successfully outlined the specific requirements for the upcoming Gum Springs project. Clear guidelines and deadlines have been established, particularly for soil testing and reporting.