Daily Field Report

Date :04/25/2024
Project No :2023C111
Client Company :2MATL
Arrival Time :04/25/2024
Onsite Hours :
Name of the Project :DOA Fiber Infrastructure Improvements
Project Location :HJAIA
Weather :
Departure Time :04/25/2024
ASEC Technician Name :Zabihullah Lodin

Observations/Finding

As requested, our AS Engineering & Consulting (ASEC) representative was on site to observe the following:

  • The placement of backfill soils for DOA Fiber infrastructure from 70 feet south from the existing comm manhole continued this day.
  • At the time of our arrival our representative observed the work in progress with duct bank backfill being placed and compacted using trench compactor equipment.  Density testing was performed using a nuclear density guarge.
  • Density test results indicate that the compacted materials met the compaction requirement of 90% of a standard proctor (ASTM 689). 

 

 

 

 

Technician Signature / DateZabihullah Lodin, April 25, 2024
Reviewer Name / DateKenneth Mosman, July 10, 2024