- Daily Field Report Report ID: 67304
- Edit Download Report
Daily Field Report
Date :04/17/2024
Project No :2023C111
Client Company :2MATL
Arrival Time :04/17/2024
Onsite Hours :
Name of the Project :DOA Fiber Infrastructure Improvements
Project Location :HJAIA
Weather :
Departure Time :04/18/2024
ASEC Technician Name :
Observations/Finding
As requested, our AS Engineering & Consulting representative was on site to observe daily activities. Today, the following was observed:
- The placement of backfill for the DOA Fiber infrastructure from 35 feet west of the east end, T/W SG runway 28-10 continued on this day.
- At the time of our arrival our representative observed that work was in progress with duct bank backfill being placed and compacted using trench compactor equipment. Density testing was performed using a nuclear density gauge.
- Density test results indicate that the compacted materials met the requirement of 90% of a standard proctor (ASTM 689).
Technician Signature / DateZabihullah Lodin, April 17, 2024
Reviewer Name / DateKenneth Mosman, July 10, 2024