Daily Field Report

Date :03/25/2024
Project No :2023C111
Client Company :2MATL
Arrival Time :03/25/2024 10:00
Onsite Hours :
Name of the Project :DOA Fiber Infrastructure Improvements
Project Location :HJAIA
Weather :
Departure Time :03/26/2024
ASEC Technician Name :Zabihullah Lodin

Observations/Finding

As requested, our AS Engineering & Consulting representative was on site to observe daily activities.  The following were observed this day:

  • The placement of backfill soils for the DOA Fiber infrastructure duct bank and installation of manhole at location R12 continued on this day.
  • At the time of our arrival our representative observed that work was in progress with duct bank being backfilled and compacted using a trench compactor.  Density testing was performed using a nuclear density gauge.
  • Density test results indicate that the compacted materials met the requirement of 90% of a standard proctor (ASTM 689). 

 

 

 

 

Technician Signature / DateZabihullah Lodin, March 25, 2024
Reviewer Name / DateKenneth Mosman, July 10, 2024