Daily Field Report

Date :06/17/2024
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :06/17/2024 08:00
Onsite Hours :9:30
Name of the Project :Lakeside Sub. - Lovers Lane, Calhoun
Project Location :Calhoun
Weather :Sunny
Departure Time :06/17/2024 17:30
ASEC Technician Name :Marteze Jeter

Observations/Finding

At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications.  The following observations were made on site this shift:

Our representative observed the contractor use a CAT 336 and CAT 3151 to excavate a water main and 1-foot riser to manholes. A Sany SY365C was used to excavate sewer trench from MH 6.9-6.10. A Sany SY365C was used to place 26-feet of SDR Sewer laterals. Contractors used a CAT 938k loader to transport No. 57 stone and GAB. No. 57 stone was added to 6 inches above the sanitary sewer later. GAB and backfill was added from MH 9.0-10.0 and compacted using a walk behind roller.

A Komatsu 61pxi dozer was used to compact and form Lots #16 through #18. A walk-behind roller was used to compact soil in 6-inch lifts.

Observations:

  1. Backfilling Activities:   Contractors placed backfill in sewer laterals and storm trenches. Also Added 6 inches of No. 57 stone then GAB.
  2. Storm Drainpipe Installation:  Contractors inserted sewer laterals.

Conclusion: The ongoing backfilling and storm drainpipe installation activities are progressing as planned.

Technician Signature / DateMarteze Jeter, June 17, 2024
Reviewer Name / DateKenneth Mosman, July 20, 2024