Density Test Report

Date :06/06/2024
Project No :2024C112
Client Company :SR Homes
Arrival Time :06/06/2024 8:30
Onsite Hours :9:00
Name of the Project :Sterlington
Project Location :Canton
Weather :cloudy
Departure Time :06/06/2024 17:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
06/06/2024 1 15.7 101.0 P-02 105.9 18.8 95.4 95 D6938 Pass
Location : Lot #9, Elv/Depth :1 foot below finished grade
Comment : Gauge Serial No. :38069
06/06/2024 2 16.2 99.7 P-02 105.9 18.8 94.1 95 D6938 Fail
Location : Lot #8, Elv/Depth :at finished grade
Comment : Gauge Serial No. :38069
06/06/2024 3 15.9 101.4 P-02 105.9 18.8 95.8 95 D6938 Pass
Location : Lot #7, Elv/Depth :at finished grade
Comment : Gauge Serial No. :38069
Technician Signature / DateAminullah Azimi, June 6, 2024
Reviewer Name / DateKenneth Mosman, July 18, 2024