- Daily Field Report Report ID: 66712
- Edit Download Report
Daily Field Report
Date :05/24/2024
Project No :2023C141
Client Company :Toll Bros
Arrival Time :05/24/2024 8:30
Onsite Hours :02:30
Name of the Project :N. Gate - Old Atlanta Road
Project Location :Cumming
Weather :sunny
Departure Time :05/24/2024 11:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to visually observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site this shift:
- A proof-roll observation was performed on the subbase for a portion of roadway as shown in red in the attached sketch.
- A fully loaded tandem-axle dump truck was used to proof-roll the above-mentioned subgrade with multiple passes across the area.
- No severe yielding and/or deflection was observed during the proof-roll at all areas mentioned above (except a few small areas as shown in yellow in the attached sketch). It was recommended to undercut to a depth of 6′ and replace with GAB.
Technician Signature / DateAminullah Azimi, May 24, 2024
Reviewer Name / DateKenneth Mosman, July 15, 2024