Daily Field Report
Date :05/15/2024
Project No :2022C106
Client Company :CWM
Arrival Time :05/15/2024 8:00
Onsite Hours :08:00
Name of the Project :Taxiway 2022 Pavement Replacement
Project Location :HJAIA
Weather :sunny
Departure Time :05/15/2024 16:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative, Amin Azimi visited the job site to observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site this shift:
- A pre-pour observation was performed in the NLVR located on taxiway 2022 phase 7, on this day. The contractor completed rebar and dowel basket placement.
- The writer visually inspected the installation and setup of these lanes and advised the contractor representatives of any minor corrections that were required.
- Contractor cleaned loose rock and debris and puddles of water from the base.
- Baskets were found to be level and straight and secured.
- Dowel bars have epoxy. Embedment depth was found to be 15″ into concrete.
- The reinforcing steel was checked for correct size, number of bars, location of bars, spacing, cleanliness, support against displacement, splicing, clearance and steel grade. Based on visual observations and field measurements, the reinforcing steel at the utility panel, appeared to be acceptable for size, spacing and quantity.
Our representative along with Thomas of ATLQA and Braylyn the ATLNext.
In case of any questions or concerns with regards to our observations or recommendations stated in this report we will be more than glad to discuss them with you.
Technician Signature / DateAminullah Azimi, May 15, 2024
Reviewer Name / DateKenneth Mosman, July 12, 2024