Daily Field Report

Date :05/10/2024
Project No :2021C002
Client Company :CW Matthews
Arrival Time :05/10/2024 8:00
Onsite Hours :9:00
Name of the Project :Runway 9L End Around Taxiway
Project Location :HJAIA
Weather :cloudy
Departure Time :05/10/2024 17:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

  • The placement and compaction of backfill M10 and GAB located at bend 30 at STA 7021+32.82 and observed the subcontractor (Lewis contracting) as they began backfilling in the area of the manhole placed at the 30″ in-line valve approximately at STA 7016+27, and also observed the placement of 9 cubic yards, 3000 psi concrete for bent 30 approximately at STA 7021+32.82.
  • At the time of arrival, our representative observed that work was in progress with 6-inch lifts being placed and compacted using a trench and jumping jack plat compactor.
  • Density test results indicate that the compacted materials met the project requirement of 95% of the maximum dry density obtained by the Modified  Proctor ASTM D1557.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateAminullah Azimi, May 10, 2024
Reviewer Name / DateKenneth Mosman, July 10, 2024