- Daily Field Report Report ID: 66413
- Edit Download Report
Daily Field Report
Date :05/08/2024
Project No :2022C165
Client Company :Toll Bros. Inc.
Arrival Time :05/08/2024 10:00
Onsite Hours :06:00
Name of the Project :Northfield @ Polo Fields - Phase2
Project Location :Pittman Road, Cumming, GA
Weather :Cloudy
Departure Time :05/08/2024 16:
ASEC Technician Name :Fawad Shagiwal
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.
The following observations were observed on the site this day.
- Three layers of 14312.7 cubic feet of large “surge stone” was placed and compacted in the new pond behind the Lot #22 using Excavator (PC390LC) equipment.
- Four layers of 10044 cubic feet of soil was placed and compacted in the new pond behind the Lot #22 using Excavator (PC390LC) equipment.
Technician Signature / DateFawad Shagiwal, May 8, 2024
Reviewer Name / DateKenneth Mosman, July 10, 2024