- Home
- Daily Field Report Report ID: 66043
- Edit Download Report
Daily Field Report
Date :04/18/2024
Project No :2022C106
Client Company :CWM
Arrival Time :04/18/2024 8:00
Onsite Hours :08:00
Name of the Project :Taxiway 2022 Pavement Replacement
Project Location :HJAIA
Weather :sunny
Departure Time :04/18/2024 16:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site this shift:
- Kelly was stripping topsoil east of eastern shoulder and west of western shoulder of the Taxiway phase 7A to place SQD.
- BBH installed power lines in the above location for lights.
- Performed straightedge on concrete for lanes 1-4 phase 7A.
- Various lab work was performed.
- Observed concrete coring from lane 1-4, phase 7A for the following:
- Lane 1-1, phase 7A, 20.5″, panel 3 from west end.
- Lane 2-1, phase 7A, 21″, panel 2 from west end.
- Lane 3-1, phase 7A, 20.5″, panel 4 from east end.
- Lane 4-1 phase 7A, 22-3/4″, panel 6 from west end.
- Lane 4-2 phase 7A, 22.5″, panel 7 from east end.
In case of any questions or concerns with regards to our observations or recommendations stated in this report we will be more than glad to discuss them with you.
Technician Signature / DateAminullah Azimi, April 18, 2024
Reviewer Name / DateKenneth Mosman, May 23, 2024