- Home
- Daily Field Report Report ID: 66035
- Edit Download Report
Daily Field Report
Date :04/17/2024
Project No :2022C106
Client Company :CWM
Arrival Time :04/17/2024 6:00
Onsite Hours :12:00
Name of the Project :Taxiway 2022 Pavement Replacement
Project Location :HJAIA
Weather :sunny
Departure Time :04/17/2024 18:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site this shift:
- A proof-roll observation was performed on the shoulder located in the east of Taxiway 22 phase 7B.
- A fully loaded water truck was used to proof-roll the above-mentioned subgrade with multiple passes across the area.
- No severe yielding and/or deflection was observed during the proof-roll at all areas mentioned above.
- Our representative along with Thomas of ATLQA and the ATLNext representative Braylyn observed the proof-roll.
- Installation of power lines for lights at western shoulder performed.
- ATL paving poured asphalt at eastern and western shoulder of phase 7A.
- Observed the placement and testing of concrete for west curb project at east roadway inside lane. from STA 107+40 to 108+90.
- Concrete observed on this date appeared to be placed in compliance with project specifications with regard to temperature, slump, air content, and batch to placement time.
Technician Signature / DateAminullah Azimi, April 17, 2024
Reviewer Name / DateKenneth Mosman, May 23, 2024