- Home
- Daily Field Report Report ID: 66027
- Edit Download Report
Daily Field Report
Date :04/16/2024
Project No :2022C106
Client Company :CWM
Arrival Time :04/16/2024 8:00
Onsite Hours :08:00
Name of the Project :Taxiway 2022 Pavement Replacement
Project Location :HJAIA
Weather :sunny
Departure Time :04/16/2024 16:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative, Amin Azimi visited the job site to observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site this shift:
- CWM drilled north edge of concrete lane 1, for dowels.
- BBH was installing power line at eastern shoulder of phase 7A and phase 7B.
- Kelly was installing under drains at 7A western shoulder parallel to the edge of concrete, and backfilling with #89 stone.
- Performed lab work on this day,
In case of any questions or concerns with regards to our observations or recommendations stated in this report we will be more than glad to discuss them with you.
Technician Signature / DateAminullah Azimi, April 16, 2024
Reviewer Name / DateKenneth Mosman, May 23, 2024