Daily Field Report

Date :03/20/2024
Project No :2023C159
Client Company :CW Matthews
Arrival Time :03/20/2024 12:00
Onsite Hours :04:00
Name of the Project :Airfield Repairs 2021-23
Project Location :HJAIA, Atlanta, GA
Weather :sunny
Departure Time :03/20/2024 16:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative, Amin Azimi visited the job site to observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications.  The following observations were made on site this shift:

Observed the placement of 8 cubic yards 4000 psi concrete for 27R Slop repair storm water western MH.

Concrete observed on this date appeared to be placed in compliance with project specifications with regard to temperature, air content, and batch to placement time.

In case of any questions or concerns with regards to our observations or recommendations stated in this report we will be more than glad to discuss them with you.

Technician Signature / DateAminullah Azimi, March 20, 2024
Reviewer Name / DateKenneth Mosman, March 28, 2024