Daily Field Report
Date :03/22/2024
Project No :2022C165
Client Company :Toll Bros. Inc.
Arrival Time :03/22/2024 08:00
Onsite Hours :05:00
Name of the Project :Northfield @ Polo Fields - Phase2
Project Location :Pittman Road, Cumming, GA
Weather :Sunny
Departure Time :03/22/2024 13:00
ASEC Technician Name :Fawad Shagiwal
Observations/Finding
- As requested, the site was visited by our AS Engineering and Consulting (ASEC)representative for the purpose of providing quality control inspection and testing services.
The following observations were observed on the site this day. - Placement, compaction and backfilling of soil at the vicinity of Lots #49 to 50 were in progress using sheeps-foot (CP56B), (QT-2) and (DZ-6) compactors.
- Excavation, soil placement and compaction at the vicinity of Lots# 27 to 29 progressed using a sheeps-foot (CP44B) and excavator (PC390LC) and (D8) equipment.
- Placement and compaction of backfill soil for the sewer pipe trench between MH A6 to MH A7 progressed.
- Excavation for placement and installation of MH A7 was in progress.
Technician Signature / DateFawad Shagiwal, March 22, 2024
Reviewer Name / DateKenneth Mosman, March 28, 2024