Density Test Report

Date :02/28/2024
Project No :2023C111
Client Company :2MATL
Arrival Time :02/26/2024 22:00
Onsite Hours :08:00
Name of the Project :DOA Fiber Infrastructure Improvements
Project Location :HJAIA
Weather :clear night
Departure Time :02/27/2024 06:00
ASEC Technician Name :Isaac Davis

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
02/27/2024 1 24.2 96.9 0 Infinity 80 D6938 Pass
Location : Mike 18 to 20, Elv/Depth :4 feet below finished grade
Comment : RTR tower-Fiber Gauge Serial No. :
02/27/2024 02 30.2 89.7 brown sandy silt mica 0 Infinity 80 D6938 Pass
Location : , Elv/Depth :4ft
Comment : RTR tower-Fiber Gauge Serial No. :
Technician Signature / DateIsaac Davis, February 28, 2024
Reviewer Name / DateKenneth Mosman, March 15, 2024