- Home
- Daily Field Report Report ID: 64317
- Edit Download Report
Daily Field Report
Date :02/21/2024
Project No :2023C141
Client Company :Toll Bros
Arrival Time :02/21/2024 15:30
Onsite Hours :02:30
Name of the Project :N. Gate - Old Atlanta Road
Project Location :Cumming
Weather :sunny
Departure Time :02/21/2024 18:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
- The placement and compaction of backfill soils for the sewer pipe between manholes A7 and A8, continued this day.
- At the time of arrival, our representative observed that work was in progress with 1-foot lifts being placed and compacted using trench compaction equipment.
- Density test results indicate that the compacted materials met the project requirement of 90% of the maximum dry density obtained by the (Standard Proctor ASTM 698),
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.
Technician Signature / DateAminullah Azimi, February 21, 2024
Reviewer Name / DateKenneth Mosman, March 15, 2024