- Density Test Report Report ID: 63696
- Edit Download Report
Density Test Report
Date :01/16/2024
Project No :2023C111
Client Company :2MATL
Arrival Time :01/16/2024 09:00
Onsite Hours :05:00
Name of the Project :DOA Fiber Infrastructure Improvements
Project Location :HJAIA
Weather :sunny
Departure Time :01/16/2024 14:00
ASEC Technician Name :Isaac Davis
Observations/Finding
Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
---|---|---|---|---|---|---|---|---|---|---|
01/16/2024 | 01 | 23 | 99.8 | 0 | Infinity | 95 | D6938 | Pass | ||
Location : | Vault #1, Elv/Depth :6 inches | |||||||||
Comment : | Finished with compaction of 90.5 (91%) | Gauge Serial No. : | ||||||||
01/16/2024 | 02 | 17.8 | 106.7 | 0 | Infinity | 95 | D6938 | Pass | ||
Location : | Vault #1, Elv/Depth :6 inches | |||||||||
Comment : | Finished with compaction of 96.7 (97%) | Gauge Serial No. : |
Technician Signature / DateIsaac Davis, January 16, 2024
Reviewer Name / DateKenneth Mosman, March 10, 2024