- Home
- Daily Field Report Report ID: 62795
- Edit Download Report
Daily Field Report
Date :10/31/2023
Project No :2023C144
Client Company :CCG
Arrival Time :10/31/2023 8:30
Onsite Hours :04:00
Name of the Project :Carodel Farms @ Union Church Rd
Project Location :Flowery Branch
Weather :sunny
Departure Time :10/31/2023 12:30
ASEC Technician Name :Aminullah Azimi
Observations/Finding
At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site this shift:
- A proof-roll observation was performed on the roadway in the front of Lots #86 to 93,
- A fully loaded tandem-axle dump truck was used to proof-roll the above-mentioned subgrade with multiple passes across the area.
- No severe yielding or deflection was observed during the proof-roll at all areas mentioned above with the exception of two soft areas (10’x40′) in the front of Lot #89 and (12’x20′) in the front of Lot # 85. It was recommended to remove the soft soils to a depth of 6″ and replaced with GAB and compact the area.
Technician Signature / DateAminullah Azimi, October 31, 2023
Reviewer Name / DateKenneth Mosman, November 12, 2023