Daily Field Report

Date :10/29/2023
Project No :2022C218
Client Company :CW Matthews
Arrival Time :10/29/2023 8:00
Onsite Hours :08:00
Name of the Project :Ramp 20 Pavement Replacement - IFB-1230102
Project Location :HJAIA
Weather :sunny
Departure Time :10/29/2023 16:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative, Amin Azimi visited the job site to observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications.  The following observations were made on site this shift:

  • ATL Paving placed approximately 6 inches of Cement Treated Base (CTB) for lanes 13 to 17.

Technician Signature / DateAminullah Azimi, October 29, 2023
Reviewer Name / DateKenneth Mosman, November 12, 2023