- Home
- Daily Field Report Report ID: 62310
- Edit Download Report
Daily Field Report
Date :10/06/2023
Project No :2023C144
Client Company :CCG
Arrival Time :10/06/2023 8:00
Onsite Hours :08:00
Name of the Project :Carodel Farms @ Union Church Rd
Project Location :Flowery Branch
Weather :sunny
Departure Time :10/06/2023 16:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
- The placement and compaction of backfill soils for road located to the north of Lots #11, 12, 13, and 14, and water storm trench between MH 62 and MH 63, and also backfill of rocks for road located to the north of lot 1, to lot 8, continued this day.
- At the time of arrival, our representative observed that work was in progress with one (1) foot lifts being placed at finished grade and compacted using 15-ton compaction equipment. and observed work was on progress with (2) foot lifts being placed for roadway north of Lots #1 to Lot #8 (see attached photos).
- Density test results indicate that the compacted materials met the project requirement of 90% of the maximum dry density obtained by the (Standard Proctor ASTM 698),
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.
Technician Signature / DateAminullah Azimi, October 6, 2023
Reviewer Name / DateKenneth Mosman, October 08, 2023