Daily Field Report

Date :09/25/2023
Project No :2022C235
Client Company :Jackson Demolition Service, Inc.
Arrival Time :09/25/2023 6:00
Onsite Hours :10:30
Name of the Project :Plant Gorgas Demolition and Grading
Project Location :460 Gorgas Rd, Parrish, AL 35580
Weather :Sunny
Departure Time :09/25/2023 16:30
ASEC Technician Name :Avinash Bandham

Observations/Finding

AS ENGINEERING AND CONSULTING, LLC (ASEC) representative Avinash Bandam visited the site at the request of Jackson Demolition representative Josh Kelly. The undersigned representative was present to monitor, verify and document the ongoing project activities. (Reference drawing E720661 S1 – R8, E720659 S1-R8.)
During the visit, the following observations were made:

1. Transportation of material for structural fill has been stopped as an elevation of 280 ft was achieved.
2. No tests have been performed on this day.
3. Basement perimeter wall was chipped using a jack hammer attachment.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Highlighted region depicts section 1

Hauling is performed in section 1

Crushing of stones in section 1

Technician Signature / DateJayanth Pillamari, September 25, 2023