Daily Field Report

Date :09/20/2023
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :09/20/2023 09:00
Onsite Hours :04:00
Name of the Project :Lakeside
Project Location :Calhoun
Weather :Sunny
Departure Time :09/20/2023 13:00
ASEC Technician Name :Vidal Dias

Observations/Finding

The undersigned ASEC representative was on-site on September 20, 2023, to observe excavation of five test pits just north of the pond to evaluate a berm for potential in-situ soils that could be re-used as structural fill material. The objective was to assess the soil conditions and provide engineering recommendations for the cut depths required to reach grade.


Test Pit Excavation and Evaluation

Test Pit Locations and Cut Depths

  • Test Pit 1: 4-foot cut to grade
  • Test Pit 2: 4-foot cut to grade
  • Test Pit 3: 5-foot cut
  • Test Pit 4: 6-foot cut
  • Test Pit 5: 8-foot cut

Technician Signature / DateVidal Dias, September 20, 2023
Reviewer Name / DateKenneth Mosman, September 24, 2023