AS ENGINEERING AND CONSULTING, LLC (ASEC) representative Avinash Bandam visited the site at the request of Jackson Demolition representative Josh Kelly. The undersigned representative was present to monitor, verify and document the ongoing project activities. (reference drawing E720661 S1 – R5, E720659 S1-R5.)
During the visit, the following observations were made:
- Three thousand three hundred and sixty-six (3366) cubic yards of structural-fill materials were placed for 8-inch lift (3) in section 1 area B7 (drawing E720661) and continued the placement of in the section 2 for lift (3) are G7 (drawing E720659) of the basement. The materials were placed in accordance with ITP-001, and the fill area is highlighted in purple on the attached drawing.
- No testing was performed on this day. Testing of section 1 and section 2 is planned to be performed the next day or at the completion of the entire lift. Therefore, no density reports were generated on this day.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.
Highlighted region depicts section 1
Highlighted region depicts section 2 part 2
Lift is placed on section 1
Hauling of structural field material in section 2