Skip to content

Daily Field Report

Date :08/14/2023
Project No :2022C218
Client Company :CW Matthews
Arrival Time :08/14/2023 9:00
Onsite Hours :08:00
Name of the Project :Ramp 20 Pavement Replacement - IFB-1230102
Project Location :HJAIA
Weather :sunny
Departure Time :08/14/2023 17:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications.  The following observations were made on site this shift:

  • A pre-pour observation was performed in the Ramp 20, phase 3, Lane 1 and Lane 10, portions of the project this day.  The contractor completed rebar and dowel basket placement for these lanes.
  • The writer visually inspected the installation and setup of these lanes and advised the contractor representatives of any minor corrections that were required.
  • Contractor cleaned loose rock and debris and puddles of water from the base.
  • Baskets were found to be level and straight and secured as per job specifications.
  • Dowel bars have epoxy. Embedment depth into the concrete was found to be 15 inches.
  • Our representative along with Ashud of ATLQA and the ATLNext representative Cornel and CWM rep Brandon signed the pre-pour card.

Technician Signature / DateAminullah Azimi, August 14, 2023
Reviewer Name / DateKenneth Mosman, September 17, 2023