Skip to content

Daily Field Report

Date :08/02/2023
Project No :2022C235
Client Company :Jackson Demolition Service, Inc.
Arrival Time :08/02/2023 06:00
Onsite Hours :10:30
Name of the Project :Plant Gorgas Demolition and Grading
Project Location :460 Gorgas Rd, Parrish, AL 35580
Weather :SUNNY
Departure Time :08/02/2023 16:30
ASEC Technician Name :Avinash Bandham

Observations/Finding

 

AS ENGINEERING AND CONSULTING, LLC (ASEC) representative Avinash Bandam visited the site at the request of Jackson Demolition representative Josh Kelly. The undersigned representative was present to monitor, verify and document the ongoing project activities. (Reference drawing E720661 S1 – R8, E720659 S1-R8.)

During the visit, the following observations were made:

  1. Two thousand five hundred and two (2502) cubic yards of fill materials were placed for lift (26) in section 1 basement area G7 (E720661 S1-R8). The materials were placed and compacted in accordance with ITP-001, and the fill area is highlighted in brown as depicted in the attached drawing.
  2. No testing was performed on this day. Testing of section 1 and section 2 is planned to be performed the next day or at the completion of the entire lift. Therefore, no density reports were generated on this day.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Highlighted region shows the placement area of fill material

Placement of fill material in section 1

Placement of fill material in section 1

Started the placement of fill material in section 1

Technician Signature / DateAvinash Bandham, August 2, 2023
Reviewer Name / DateRamchandra Mogulla, August 07, 2023