Skip to content

Daily Field Report

Date :07/31/2023
Project No :2022C235
Client Company :Jackson Demolition Service, Inc.
Arrival Time :07/31/2023 06:00
Onsite Hours :10:30
Name of the Project :Plant Gorgas Demolition and Grading
Project Location :460 Gorgas Rd, Parrish, AL 35580
Weather :SUNNY
Departure Time :07/31/2023 16:30
ASEC Technician Name :Avinash Bandham

Observations/Finding

Our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative Avinash Bandam visited the site at the request of Jackson Demolition representative Josh Kelly. The undersigned representative was present to observe, verify and document the ongoing project activities. (Reference drawing E720661 S1 – R8, E720659 S1-R8.).

During the visit, the following observations were made:

  1. Two thousand one hundred and twenty-four (2124) cubic yards of fill materials were placed for lift (23) in section 2 basement area G7 (E720659 S1-R8). The materials were placed and compacted in accordance with ITP-001, and the fill area is highlighted in brown as depicted in the attached drawing.
  2. The basement area was probed using the 3/8″ diameter probe rod.  In addition, three moisture density tests were performed in the basement followed with a check-plug to verify the density test results with the Moisture-Density Relationship. The test locations are marked on the enclosed drawing.

Fill-materials are placed in section 2 basement area G7 part 2

Fill-materials are placed in section 2 basement area G7 part 2

The highlighted region shows the placement of fill-material

Technician Signature / DateAvinash Bandham, July 31, 2023
Reviewer Name / DateRamchandra Mogulla, August 02, 2023