- Daily Field Report Report ID: 60408
- Edit Download Report
Daily Field Report
Date :07/18/2023
Project No :2022C178
Client Company :CW Matthews
Arrival Time :07/18/2023 8:30
Onsite Hours :05:00
Name of the Project :Ramp 2 Pavement Replacement
Project Location :HJAIA
Weather :sunny
Departure Time :07/18/2023 13:30
ASEC Technician Name :Aminullah Azimi
Observations/Finding
At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to observe the contractor’s work activities from a quality standpoint to assure compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site this shift:
- A proof-roll observation was performed on the Ramp 2, phase 10.
- A fully loaded tandem-axle dump truck was used to proof-roll the above-mentioned subgrade with multiple passes across the area.
- Some yielding and deflection were observed during the proof-roll at all areas mentioned above.
- Our representative along with Ashud of ATLQA and the ATLNext representative Hazim observed the proof-roll.
- The under drain was cut and backfilled with #81 stone.
Technician Signature / DateAminullah Azimi, July 18, 2023
Reviewer Name / DateKenneth Mosman, July 30, 2023